Q1. - (Topic 1)
Which of the following statements about the Project Initiation Documentation are true?
1.
The Project Initiation Documentation is used to ensure that a sound basis exists before the Project Board authorizes a project.
2.
The Project Initiation Documentation should be updated at the end of each stage to reflect the current status of a project.
A. Only 1 is true
B. Only 2 is true
C. Both 1 and 2 are true
D. Neither 1 or 2 are true
Answer: C
Q2. - (Topic 1)
Which is NOT a purpose of the Organization theme?
A. Define a project management team structure
B. Define the level of tolerance for each level of the project management team
C. Define the Project Board's responsibility for directing the project
D. Define which role is accountable for the project's success
Answer: B
Q3. - (Topic 1)
Which is an objective of the Initiating a Project process?
A. Develop the corporate quality management system as part of the Project Initiation Documentation
B. Prepare the plans for the subsequent stages
C. Summarize how the organization's project management method will be tailored for the project
D. Request authority from corporate management to deliver the project
Answer: C
Q4. - (Topic 1)
Identify the missing words in the following sentence. A project is [ ? ] organization that is created for the purpose of delivering business products.
A. a corporate
B. a temporary
C. an external
D. a technical
Answer: B
Q5. - (Topic 1)
Which is a benefit of using PRINCE2?
A. Enables the management of projects as well as of 'business as usual' activities
B. Can be tailored by leaving out elements of the method for some projects
C. Can be applied to any type of project
D. Avoids the need to involve corporate or programme management
Answer: C
Q6. - (Topic 2)
Identify the missing words in the following sentence. A purpose of the Plans theme is to [ ? ] the project's plans.
A. define a coding system to provide a unique identifier for the products within
B. summarize the results of the quality activities performed on
C. provide a framework to design, develop and maintain
D. define the project benefits to be achieved by each of
Answer: C
Q7. - (Topic 1)
Which does the Executive need to ensure is in place before the project is initiated?
A. All Work Packages are authorized
B. An understanding of how the project will contribute to corporate objectives
C. The Project Plan has been approved
D. The Project Initiation Documentation is complete
Answer: B
38. - (Topic 1)
What is the collective name for individuals or groups who may be affected by a project?
A. Customers
B. Project Support
C. Stakeholders
D. Team members
Q8. - (Topic 1)
Which of the following statements about the Project Initiation Documentation are true?
1.
The Project Initiation Documentation is used to ensure that a sound basis exists before the Project Board authorizes a project.
2.
The Project Initiation Documentation should be updated at the end of each stage to reflect the current status of a project.
A. Only 1 is true
B. Only 2 is true
C. Both 1 and 2 are true
D. Neither 1 or 2 are true
Answer: C
Q9. - (Topic 2)
Which is one of the three levels of plan in PRINCE2?
A. Benefits Review Plan
B. Programme Plan
C. Team Plan
D. Project Brief
Answer: C
Q10. - (Topic 2)
Which is a recommended quality review team role?
A. Project Manager
B. Assurance
C. Project Support
D. Administrator
Answer: D