Master the 1z0-1008 Oracle Project Portfolio Management Cloud 2021 Implementation Essentials content and be ready for exam day success quickly with this Passleader 1z0-1008 test questions. We guarantee it!We make it a reality and give you real 1z0-1008 questions in our Oracle 1z0-1008 braindumps.Latest 100% VALID Oracle 1z0-1008 Exam Questions Dumps at below page. You can use our Oracle 1z0-1008 braindumps and pass your exam.

NEW QUESTION 1
Your customer wants to calculate Estimate to Complete (ETC) as the difference between Current
Planned Cost and Actual Cost. In Progress Settings, which option would you use in conjunction with the ETC method to meet this requirement? (Choose the best answer.)

  • A. Effort

  • B. Cost

  • C. Manual Entry

  • D. Remaining Plan

Answer: B

Explanation:
Reference:
https://ppm-help.saas.hpe.com/en/9.42/Help/Content/UG/PjMUG/view_pj_cost_data_costtab.htm

NEW QUESTION 2
Identify two correct role templates available on the Oracle Entitlement Server to generate roles for
Project Organization Security. (Choose two.)

  • A. Project Manager Template for Project Organization Security

  • B. Project Administrator Template for Project Organization Security

  • C. Project Creator Template for Project Organization Security

  • D. Project Accountant Template for Project Organization Security

  • E. Project Billing Specialist Template for Project Organization Security

Answer: AD

Explanation:
Reference:
https://docs.oracle.com/cloud/latest/common/FASER/FASER2406048.htm#FASER2406048

NEW QUESTION 3
Which three are part of using the Rapid Implementation for Project Financial Management Applications macro-enabled Microsoft Excel spreadsheet to enter setup data?

  • A. Prepare setup data.

  • B. Import Projects.

  • C. Generate CSV files.

  • D. Upload setup data.

  • E. File Import and Export.

Answer: ACD

Explanation:
https://docs.oracle.com/applications/farel12/projectop_gs/OAPFM/OAPFM2264569.htm#OAPFM21 59921

NEW QUESTION 4
You are trying to create a custom infolet, but are not able to find the "Create Infolet" option in the
Infolet repository window. Which two steps should be completed before you can access the "Create Infolet" option?

  • A. You must activate Page Composer.

  • B. You should be on the Project Custom Objects page.

  • C. You must be in an active sandbox.

  • D. You should enable the "Create Infolet" option from the Personalize Springboard page.

Answer: D

NEW QUESTION 5
Which three are true of what you can do in the Project Requirements work area?

  • A. Create an implementation project.

  • B. Organize backlog items by requirements.

  • C. Create an execution project.

  • D. Create project tasks for backlog items.

  • E. Manage your list of backlog items.

Answer: BCD

NEW QUESTION 6
Which application generates external roles to grant both function and data security? (Choose the
best answer.)

  • A. Authorization Policy Manager

  • B. Oracle Identity Manager

  • C. Business Process Manager

  • D. Functional Setup Manager

Answer: B

Explanation:
Reference:
https://docs.oracle.com/cd/E60665_01/common/FASER/FASER1349817.htm#FASER1722625

NEW QUESTION 7
Identify the precedence order in which cost rates are determined for a planning resource when
deriving raw costs for rate-based planning resources. (Choose the best answer.)

  • A. Override rate > Job rate schedule > Resource class rate schedule > Person rate schedule

  • B. Person rate schedule > Job rate schedule > Resource class rate schedule > Override rate

  • C. Job rate schedule > Resource class rate schedule > Override rate > Person rate schedule

  • D. Override rate > Person rate schedule > Job rate schedule > Resource class rate schedule

  • E. Resource class rate schedule > Override rate > Job rate schedule > Person rate schedule

Answer: D

Explanation:
Reference:
https://fusionhelp.oracle.com/helpPortal/topic/TopicId_P_8718794B26A7BB93E040D30A688149A3

NEW QUESTION 8
Your organization performs revenue recognition based on the Labor and Non-labor Burden schedule types. Identify the setup required to enable this kind of revenue recognition. (Choose the best answer.)

  • A. Create a revenue method with a revenue method classification of Amount Based.

  • B. Create a revenue method with a revenue method classification of Rate Based.

  • C. Create a revenue method classification with a revenue method of Percent Spent.

  • D. Create a revenue method classification with a revenue method of Percent Complete.

Answer: B

NEW QUESTION 9
A project administrator is trying to assign a team member for a project, but cannot find the person in the team member list on the Project Definition page. What is the reason for this problem? (Choose the best answer.)

  • A. The employee is not assigned to the project-owning organization.

  • B. The employee is not assigned with a supervisor.

  • C. Project roles are not assigned in the project.

  • D. The employee is not assigned to a department.

Answer: C

NEW QUESTION 10
Your customer accounts revenue based on product class category. Because all your customer's
projects are funded by private and government institutions, they decide to classify all projects based on their funding source to accurately report on revenue in General Ledger. Accordingly, you create a new class category “Funding Source”, and assign it to all projects. However, you notice that the accounting is still happening based on product class category.
Identify the reason for this problem. (Choose the best answer.)

  • A. Funding source class category is assigned to all project types.

  • B. Funding source class category is not enabled for “available as accounting source”.

  • C. Product class category is not enabled for “available as accounting source”.

  • D. Funding source class category is enabled for “available as accounting source”.

Answer: C

NEW QUESTION 11
Which three tools are available for accessing REST APIs?

  • A. cURL

  • B. Web Browser

  • C. Oracle Transactional Business Intelligence

  • D. Programming Language

Answer: ABC

NEW QUESTION 12
Your company uses an accounting calendar with periods that are identical to calendar months. A
contract resource has been identified to work for six months on an accounting close cycle project. The resource is planned to start with 10 days left in the first period and to end 20 days into the last period. For the remaining periods, the resource must be loaded on all working days of the month. You are required to distribute the budget, forecast, and planning amounts across periods based on the task duration.
Which predefined spread curve must be used to meet this requirement? (Choose the best answer.)

  • A. Daily Spread Basis

  • B. Back Loaded

  • C. Bell Curve

  • D. S-Curve

  • E. Even

Answer: D

NEW QUESTION 13
Identify the three contract attributes from Project Performance Data that are used in Project Performance dashboard regions. (Choose three.)

  • A. Expenditure Type

  • B. Projects

  • C. Contract Line

  • D. Contract Header

  • E. Task

Answer: ACE

Explanation:
Reference:
https://docs.oracle.com/cloud/farel9/projectcs_gs/FAUAR/F1537947AN10251.htm

NEW QUESTION 14
Using Oracle Time and Labor, your client wants to put in a validation process that allows only a
certain number of maximum hours an employee can charge in a day, and a minimum of hours he or she can report in a week.
What feature would you use to meet this requirement? (Choose the best answer.)

  • A. project time validation rules

  • B. time calculation rules

  • C. time entry rules

  • D. time audit rules

Answer: C

NEW QUESTION 15
Your customer has implemented Oracle Project Portfolio Management Cloud recently and they have hired new employees for their Professions Services business. These employees are set up in Oracle Human Capital Management Cloud, but the Project Administrators are unable to add them as resources in the Planning Resource Breakdown Structure.
What are three conditions for new employees to show up in the list? (Choose three.)

  • A. Current date is before the effective date of the resource, and you did not enable the “Include people with future-dated effective start dates” option during the search.

  • B. All new employees created as persons must have an active supervisor.

  • C. All new employees created as persons must be assigned to a department.

  • D. All new employees created as persons must have an active assignment.

  • E. All new employees created as persons must have an active project role.

Answer: ADE

NEW QUESTION 16
Identify three correct statements about project types. (Choose three.)

  • A. Project type can be used as a source in subledger accounting.

  • B. Project type can be enabled for both billing and capitalization.

  • C. Summarization options can be specified at project type.

  • D. Classifications can be assigned at project type.

  • E. Project type can be associated with multiple project units.

Answer: BCE

NEW QUESTION 17
Which three setups can be configured by using Rapid Implementation for Project Financial Management Applications?

  • A. Departments

  • B. Expenditure Types

  • C. Project Templates

  • D. Project Types

Answer: ABD

NEW QUESTION 18
You configure one OTBI using Project Cross Subject Area Analysis Real Time. You notice that all
measures (Budget, Forecast, Cost, Commitments, Revenue, and Invoice) are not available for Bill-To- Customer and Contract and Contract Line dimensions. Identify the reason for this behavior. (Choose the best answer.)

  • A. The Bill-To-Customer dimension applies only to Invoice measures, but the Contract and Contract Line dimensions do not apply to Revenue and Invoice measures.

  • B. The Bill-To-Customer dimension applies only to Revenue and Invoice measures.

  • C. The Contract and Contract Line dimensions apply only to Invoice measures.

  • D. The Bill-To-Customer dimension applies to Invoice measures, and the Contract and Contract Line dimensions apply to Revenue and Invoice measures.

  • E. The Bill-To-Customer dimension does not apply to Invoice measures, but the Contract and Contract Line dimensions apply only to Revenue and Invoice measures.

Answer: B

NEW QUESTION 19
Which four notification templates are predefined?

  • A. Password Reset Template

  • B. New Account Template

  • C. Forgot Password Template

  • D. Forgot Username Template

  • E. New Account Manager Template

Answer: ABCE

Explanation:
https://docs.oracle.com/en/cloud/saas/sales/18c/oscus/setting-up-applications-security.html#OSCUS2287154

NEW QUESTION 20
Identify three correct statements about the integration of Primavera P6 Enterprise Project Portfolio
Management and Oracle Project Portfolio Management Cloud. (Choose three.)

  • A. Event completion flows from Primavera P6 Enterprise Project Portfolio Management to Oracle Project Portfolio Management Cloud.

  • B. Billing events flow from Primavera P6 Enterprise Project Portfolio Management to Oracle Project Portfolio Management Cloud.

  • C. Summarized actual quantity and cost flow from Oracle Project Portfolio Management Cloud to Primavera P6 Enterprise Project Portfolio Management.

  • D. Projects and task definitions flow from Oracle Project Portfolio Management Cloud to Primavera P6 Enterprise Project Portfolio Management.

  • E. Project plans and progress flow from Oracle Project Portfolio Management Cloud to Primavera P6 Enterprise Project Portfolio Management.

Answer: CDE

NEW QUESTION 21
You are trying to create a project purchase order (PO) but you are unable to select Expenditure
Organization in the PO. Identify two reasons for this problem. (Choose two.)

  • A. The organization is not classified as a project-owning organization.

  • B. The organization is not classified as a project expenditure organization.

  • C. The organization is not included in the organization tree that is assigned to the business unit that owns the PO.

  • D. The organization is classified as a project unit.

Answer: BC

NEW QUESTION 22
Which two statements are true about a project in “Draft” status? (Choose two.)

  • A. Project managers can view draft projects on the Project Manager Dashboard and use the projectsfor requirements planning.

  • B. Project managers can neither view draft projects on the Project Manager Dashboard nor use the projects for requirements planning.

  • C. Team members can see the tasks from draft projects on the Team Member Dashboard or in the My Work work area.

  • D. Team members cannot see the tasks from draft projects on the Team Member Dashboard or in the My Work work area.

Answer: AD

NEW QUESTION 23
As you go through the first-quarter close for your customer, you notice that the burden amounts calculated do not seem to be right. Based on the calculations, you notice that the amounts calculated are not considering the burden schedule override at a task level, which was done during the second month of the quarter.
Identify the reason for this problem. (Choose the best answer.)

  • A. Only new expenditure items charged to the task use the new burden schedule; expenditure items processed earlier cannot be reprocessed.

  • B. Only new expenditure items charged to the task use the new burden schedule; expenditure items processed earlier can be manually marked for reprocessing.

  • C. You can enable automatic reprocessing of expenditure items processed before the burden schedule change.

  • D. All expenditure items charged to the task use the new burden schedule.

Answer: B

Explanation:
Reference:
https://docs.oracle.com/cloud/r13_update17b/projectcs_gs/OAPJC/OAPJC1071490.htm#OAPJC1071 482