Master the 1z0-1008 Oracle Project Portfolio Management Cloud 2021 Implementation Essentials content and be ready for exam day success quickly with this Passleader 1z0-1008 test questions. We guarantee it!We make it a reality and give you real 1z0-1008 questions in our Oracle 1z0-1008 braindumps.Latest 100% VALID Oracle 1z0-1008 Exam Questions Dumps at below page. You can use our Oracle 1z0-1008 braindumps and pass your exam.
NEW QUESTION 1
Your customer wants to calculate Estimate to Complete (ETC) as the difference between Current
Planned Cost and Actual Cost. In Progress Settings, which option would you use in conjunction with the ETC method to meet this requirement? (Choose the best answer.)
Answer: B
Explanation:
Reference:
https://ppm-help.saas.hpe.com/en/9.42/Help/Content/UG/PjMUG/view_pj_cost_data_costtab.htm
NEW QUESTION 2
Identify two correct role templates available on the Oracle Entitlement Server to generate roles for
Project Organization Security. (Choose two.)
Answer: AD
Explanation:
Reference:
https://docs.oracle.com/cloud/latest/common/FASER/FASER2406048.htm#FASER2406048
NEW QUESTION 3
Which three are part of using the Rapid Implementation for Project Financial Management Applications macro-enabled Microsoft Excel spreadsheet to enter setup data?
Answer: ACD
Explanation:
https://docs.oracle.com/applications/farel12/projectop_gs/OAPFM/OAPFM2264569.htm#OAPFM21 59921
NEW QUESTION 4
You are trying to create a custom infolet, but are not able to find the "Create Infolet" option in the
Infolet repository window. Which two steps should be completed before you can access the "Create Infolet" option?
Answer: D
NEW QUESTION 5
Which three are true of what you can do in the Project Requirements work area?
Answer: BCD
NEW QUESTION 6
Which application generates external roles to grant both function and data security? (Choose the
best answer.)
Answer: B
Explanation:
Reference:
https://docs.oracle.com/cd/E60665_01/common/FASER/FASER1349817.htm#FASER1722625
NEW QUESTION 7
Identify the precedence order in which cost rates are determined for a planning resource when
deriving raw costs for rate-based planning resources. (Choose the best answer.)
Answer: D
Explanation:
Reference:
https://fusionhelp.oracle.com/helpPortal/topic/TopicId_P_8718794B26A7BB93E040D30A688149A3
NEW QUESTION 8
Your organization performs revenue recognition based on the Labor and Non-labor Burden schedule types. Identify the setup required to enable this kind of revenue recognition. (Choose the best answer.)
Answer: B
NEW QUESTION 9
A project administrator is trying to assign a team member for a project, but cannot find the person in the team member list on the Project Definition page. What is the reason for this problem? (Choose the best answer.)
Answer: C
NEW QUESTION 10
Your customer accounts revenue based on product class category. Because all your customer's
projects are funded by private and government institutions, they decide to classify all projects based on their funding source to accurately report on revenue in General Ledger. Accordingly, you create a new class category “Funding Source”, and assign it to all projects. However, you notice that the accounting is still happening based on product class category.
Identify the reason for this problem. (Choose the best answer.)
Answer: C
NEW QUESTION 11
Which three tools are available for accessing REST APIs?
Answer: ABC
NEW QUESTION 12
Your company uses an accounting calendar with periods that are identical to calendar months. A
contract resource has been identified to work for six months on an accounting close cycle project. The resource is planned to start with 10 days left in the first period and to end 20 days into the last period. For the remaining periods, the resource must be loaded on all working days of the month. You are required to distribute the budget, forecast, and planning amounts across periods based on the task duration.
Which predefined spread curve must be used to meet this requirement? (Choose the best answer.)
Answer: D
NEW QUESTION 13
Identify the three contract attributes from Project Performance Data that are used in Project Performance dashboard regions. (Choose three.)
Answer: ACE
Explanation:
Reference:
https://docs.oracle.com/cloud/farel9/projectcs_gs/FAUAR/F1537947AN10251.htm
NEW QUESTION 14
Using Oracle Time and Labor, your client wants to put in a validation process that allows only a
certain number of maximum hours an employee can charge in a day, and a minimum of hours he or she can report in a week.
What feature would you use to meet this requirement? (Choose the best answer.)
Answer: C
NEW QUESTION 15
Your customer has implemented Oracle Project Portfolio Management Cloud recently and they have hired new employees for their Professions Services business. These employees are set up in Oracle Human Capital Management Cloud, but the Project Administrators are unable to add them as resources in the Planning Resource Breakdown Structure.
What are three conditions for new employees to show up in the list? (Choose three.)
Answer: ADE
NEW QUESTION 16
Identify three correct statements about project types. (Choose three.)
Answer: BCE
NEW QUESTION 17
Which three setups can be configured by using Rapid Implementation for Project Financial Management Applications?
Answer: ABD
NEW QUESTION 18
You configure one OTBI using Project Cross Subject Area Analysis Real Time. You notice that all
measures (Budget, Forecast, Cost, Commitments, Revenue, and Invoice) are not available for Bill-To- Customer and Contract and Contract Line dimensions. Identify the reason for this behavior. (Choose the best answer.)
Answer: B
NEW QUESTION 19
Which four notification templates are predefined?
Answer: ABCE
Explanation:
https://docs.oracle.com/en/cloud/saas/sales/18c/oscus/setting-up-applications-security.html#OSCUS2287154
NEW QUESTION 20
Identify three correct statements about the integration of Primavera P6 Enterprise Project Portfolio
Management and Oracle Project Portfolio Management Cloud. (Choose three.)
Answer: CDE
NEW QUESTION 21
You are trying to create a project purchase order (PO) but you are unable to select Expenditure
Organization in the PO. Identify two reasons for this problem. (Choose two.)
Answer: BC
NEW QUESTION 22
Which two statements are true about a project in “Draft” status? (Choose two.)
Answer: AD
NEW QUESTION 23
As you go through the first-quarter close for your customer, you notice that the burden amounts calculated do not seem to be right. Based on the calculations, you notice that the amounts calculated are not considering the burden schedule override at a task level, which was done during the second month of the quarter.
Identify the reason for this problem. (Choose the best answer.)
Answer: B
Explanation:
Reference:
https://docs.oracle.com/cloud/r13_update17b/projectcs_gs/OAPJC/OAPJC1071490.htm#OAPJC1071 482
NEW QUESTION 24
......