NEW QUESTION 1
Which of the following is a tool and technique used in the Develop Schedule process?

  • A. Three-point estimates
  • B. Resource leveling
  • C. Precedence diagramming method
  • D. Bottom-up estimating

Answer: B

NEW QUESTION 2
An output of the Create WBS process is:

  • A. Scope baseline.
  • B. Project scope statement.
  • C. Organizational process assets.
  • D. Requirements traceability matrix.

Answer: A

NEW QUESTION 3
Portfolio Management is management of:

  • A. a project by dividing the project into more manageable sub-projects.
  • B. a project by utilizing a portfolio of general management skills such as planning, organizing, staffing, executing, and controlling.
  • C. all projects undertaken by a company.
  • D. a collection of projects that are grouped together to facilitate effective management and meet strategic business objectives.

Answer: D

NEW QUESTION 4
Which quality control technique illustrates the 80/20 principle?

  • A. Ishikawa diagram
  • B. Control chart
  • C. Run chart
  • D. Pareto chart

Answer: D

NEW QUESTION 5
A tool and technique used during the Define Scope process is:

  • A. facilitated workshops.
  • B. observations.
  • C. questionnaires and surveys.
  • D. group creativity techniques.

Answer: A

NEW QUESTION 6
Payback period, return on investment, internal rate of return, discounted cash flow, and net present value are all examples of:

  • A. Expert judgment.
  • B. Analytical techniques.
  • C. Earned value management.
  • D. Group decision-making techniques.

Answer: B

NEW QUESTION 7
Project management processes ensure the:

  • A. alignment with organizational strategy
  • B. efficient means to achieve the project objectives
  • C. performance of the project team
  • D. effective flow of the project throughout its life cycle

Answer: D

NEW QUESTION 8
Cost baseline is an output of which of the following processes?

  • A. Estimate Activity Resources
  • B. Estimate Costs
  • C. Determine Budget
  • D. Control Costs

Answer: C

NEW QUESTION 9
Which tool or technique is used in the Plan Scope Management process?

  • A. Document analysis
  • B. Observations
  • C. Product analysis
  • D. Expert judgment

Answer: D

NEW QUESTION 10
Who is responsible for developing the project management plan and all related component plans?

  • A. Project team
  • B. Portfolio manager
  • C. Project manager
  • D. Project management office

Answer: C

NEW QUESTION 11
Plan Schedule Management is a process in which Knowledge Area?

  • A. Project Scope Management
  • B. Project Human Resource Management
  • C. Project Integration Management
  • D. Project Time Management

Answer: D

NEW QUESTION 12
Which of the Project Time Management processes analyzes activity sequencing, durations, resource requirements, and schedule constraints?

  • A. Estimate Activity Durations
  • B. ControlSchedule
  • C. Sequence Activities
  • D. Develop Schedule

Answer: D

NEW QUESTION 13
Which tool or technique is effective in a project in which the deliverable is not a service or result?

  • A. Inspection
  • B. Variance analysis
  • C. Decomposition
  • D. Product analysis

Answer: D

NEW QUESTION 14
As part of a mid-project evaluation, the project sponsor has asked for a forecast of the total project cost. What should be used to calculate the forecast?

  • A. BAC
  • B. EAC
  • C. ETC
  • D. WBS

Answer: B

NEW QUESTION 15
During which process would you obtain stakeholders’ formal acceptance of the completed project scope?

  • A. Quality control
  • B. Scope verification
  • C. Scope control
  • D. Close project

Answer: B

NEW QUESTION 16
Plan-do-check-act is also known as:

  • A. prevention over inspection.
  • B. statistical sampling.
  • C. management responsibility,
  • D. continuous improvement.

Answer: D

NEW QUESTION 17
Who is responsible for determining which processes from the Process Groups will be employed and who will be performing them?

  • A. Project sponsor and project manager
  • B. Project sponsor and functional manager
  • C. Project manager and project team
  • D. Project team and functional manager

Answer: C