aiotestking uk

PMP Exam Questions - Online Test


PMP Premium VCE File

Learn More 100% Pass Guarantee - Dumps Verified - Instant Download
150 Lectures, 20 Hours

Act now and download your today! Do not waste time for the worthless tutorials. Download with real questions and answers and begin to learn with a classic professional.

Free PMP Demo Online For Microsoft Certifitcation:

NEW QUESTION 1
A process is defined as:

  • A. A set of interrelated actions and activities performed to achieve a certain objective.
  • B. A set of guidelines that explains how to carry out a particular task.
  • C. The inputs for a task and the tools and techniques required to carry out the task.
  • D. A collection of logically related project activities, usually culminating in the completion of a major deliverable.

Answer: A

NEW QUESTION 2
Which process should be conducted from the project inception through completion?

  • A. Monitor and Control Project Work
  • B. Perform Quality Control
  • C. Perform Integrated Change Control
  • D. Monitor and Control Risks

Answer: C

NEW QUESTION 3
Which document defines how a project is executed, monitored and controlled, and closed?

  • A. Strategic plan
  • B. Project charter
  • C. Project management plan
  • D. Service level agreement

Answer: C

NEW QUESTION 4
Which of the following correctly explains the term "progressive elaboration'?

  • A. Changing project specifications continuously
  • B. Elaborate tracking of the project progress
  • C. Elaborate tracking of the project specifications with a change control system
  • D. Project specifications becoming more explicit and detailed as the project progresses

Answer: D

NEW QUESTION 5
A key benefit of the Manage Communications process is that it enables:

  • A. The best use of communication methods.
  • B. An efficient and effective communication flow.
  • C. Project costs to be reduced.
  • D. The best use of communication technology.

Answer: B

NEW QUESTION 6
What is a technique used in the performance reporting process?

  • A. Expert judgment
  • B. Project management methodology
  • C. Stakeholder analysis
  • D. Status review meetings

Answer: D

NEW QUESTION 7
In the Initiating Process Group, at what point does the project become officially authorized?

  • A. When the project charter is signed
  • B. When all the stakeholders agree on the scope of the project
  • C. When the project manager is appointed
  • D. When the necessary finance or funding is obtained

Answer: A

NEW QUESTION 8
Outputs of the Control Communications process include:

  • A. expert judgment and change requests.
  • B. work performance information and change requests.
  • C. organizational process asset updates and an issue log.
  • D. project management plan updates and an issue log.

Answer: B

NEW QUESTION 9
Which process involves defining, preparing, and coordinating all subsidiary plans and integrating them into a comprehensive plan?

  • A. Direct and Manage Project Work
  • B. Develop Project Management Plan
  • C. Plan Quality Management
  • D. Monitor and Control Project Work

Answer: B

NEW QUESTION 10
Ensuring that projects and programs are reviewed to prioritize resource allocation is a focus of which of the following?

  • A. Project management
  • B. Program management
  • C. Portfolio management
  • D. Relationship management

Answer: C

NEW QUESTION 11
Which of the following is an output of the Conduct Procurements process?

  • A. Project statement of work
  • B. Selected sellers
  • C. Risk register updates
  • D. Teaming agreements

Answer: B

NEW QUESTION 12
Which organizational process assets update is performed during the Close Procurements process?

  • A. Procurement audit
  • B. Lessons learned
  • C. Performance reporting
  • D. Payment requests

Answer: B

NEW QUESTION 13
Which of the following is an input to the Develop Project Charter process?

  • A. Work performance information
  • B. Project management plan
  • C. Business case
  • D. Change requests

Answer: C

NEW QUESTION 14
Which of the following processes audits the quality requirements and the results from quality control measures to ensure appropriate quality standards and operational definitions are used?

  • A. Perform Quality Control
  • B. Quality Metrics
  • C. Perform Quality Assurance
  • D. Plan Quality

Answer: C

NEW QUESTION 15
What are the five Project Management Process Groups?

  • A. Initiating, Planning, Executing, Monitoring and Controlling, and Closing
  • B. Introduction, Planning, Executing, Monitoring and Controlling, and Closing
  • C. Initiating, Planning, Executing, Monitoring and Controlling, and Ending
  • D. Introduction, Planning, Implementation, Monitoring and Controlling, and Closure

Answer: A

NEW QUESTION 16
Which activity is an input to the Conduct Procurements process?

  • A. Organizational process assets
  • B. Resource availability
  • C. Perform Integrated Change Control
  • D. Team performance assessment

Answer: A

NEW QUESTION 17
The following chart contains information about the tasks in a project.
PMP dumps exhibit
Based on the chart, what is the schedulevariance (SV) for Task 8?

  • A. -2,000
  • B. -1,000
  • C. 1,000
  • D. 2,000

Answer: B

P.S. Easily pass PMP Exam with 918 Q&As 2passeasy Dumps & pdf Version, Welcome to Download the Newest 2passeasy PMP Dumps: https://www.2passeasy.com/dumps/PMP/ (918 New Questions)