NEW QUESTION 1
A process is defined as:
- A. A set of interrelated actions and activities performed to achieve a certain objective.
- B. A set of guidelines that explains how to carry out a particular task.
- C. The inputs for a task and the tools and techniques required to carry out the task.
- D. A collection of logically related project activities, usually culminating in the completion of a major deliverable.
Answer: A
NEW QUESTION 2
Which process should be conducted from the project inception through completion?
- A. Monitor and Control Project Work
- B. Perform Quality Control
- C. Perform Integrated Change Control
- D. Monitor and Control Risks
Answer: C
NEW QUESTION 3
Which document defines how a project is executed, monitored and controlled, and closed?
- A. Strategic plan
- B. Project charter
- C. Project management plan
- D. Service level agreement
Answer: C
NEW QUESTION 4
Which of the following correctly explains the term "progressive elaboration'?
- A. Changing project specifications continuously
- B. Elaborate tracking of the project progress
- C. Elaborate tracking of the project specifications with a change control system
- D. Project specifications becoming more explicit and detailed as the project progresses
Answer: D
NEW QUESTION 5
A key benefit of the Manage Communications process is that it enables:
- A. The best use of communication methods.
- B. An efficient and effective communication flow.
- C. Project costs to be reduced.
- D. The best use of communication technology.
Answer: B
NEW QUESTION 6
What is a technique used in the performance reporting process?
- A. Expert judgment
- B. Project management methodology
- C. Stakeholder analysis
- D. Status review meetings
Answer: D
NEW QUESTION 7
In the Initiating Process Group, at what point does the project become officially authorized?
- A. When the project charter is signed
- B. When all the stakeholders agree on the scope of the project
- C. When the project manager is appointed
- D. When the necessary finance or funding is obtained
Answer: A
NEW QUESTION 8
Outputs of the Control Communications process include:
- A. expert judgment and change requests.
- B. work performance information and change requests.
- C. organizational process asset updates and an issue log.
- D. project management plan updates and an issue log.
Answer: B
NEW QUESTION 9
Which process involves defining, preparing, and coordinating all subsidiary plans and integrating them into a comprehensive plan?
- A. Direct and Manage Project Work
- B. Develop Project Management Plan
- C. Plan Quality Management
- D. Monitor and Control Project Work
Answer: B
NEW QUESTION 10
Ensuring that projects and programs are reviewed to prioritize resource allocation is a focus of which of the following?
- A. Project management
- B. Program management
- C. Portfolio management
- D. Relationship management
Answer: C
NEW QUESTION 11
Which of the following is an output of the Conduct Procurements process?
- A. Project statement of work
- B. Selected sellers
- C. Risk register updates
- D. Teaming agreements
Answer: B
NEW QUESTION 12
Which organizational process assets update is performed during the Close Procurements process?
- A. Procurement audit
- B. Lessons learned
- C. Performance reporting
- D. Payment requests
Answer: B
NEW QUESTION 13
Which of the following is an input to the Develop Project Charter process?
- A. Work performance information
- B. Project management plan
- C. Business case
- D. Change requests
Answer: C
NEW QUESTION 14
Which of the following processes audits the quality requirements and the results from quality control measures to ensure appropriate quality standards and operational definitions are used?
- A. Perform Quality Control
- B. Quality Metrics
- C. Perform Quality Assurance
- D. Plan Quality
Answer: C
NEW QUESTION 15
What are the five Project Management Process Groups?
- A. Initiating, Planning, Executing, Monitoring and Controlling, and Closing
- B. Introduction, Planning, Executing, Monitoring and Controlling, and Closing
- C. Initiating, Planning, Executing, Monitoring and Controlling, and Ending
- D. Introduction, Planning, Implementation, Monitoring and Controlling, and Closure
Answer: A
NEW QUESTION 16
Which activity is an input to the Conduct Procurements process?
- A. Organizational process assets
- B. Resource availability
- C. Perform Integrated Change Control
- D. Team performance assessment
Answer: A
NEW QUESTION 17
The following chart contains information about the tasks in a project.
Based on the chart, what is the schedulevariance (SV) for Task 8?
- A. -2,000
- B. -1,000
- C. 1,000
- D. 2,000
Answer: B