NEW QUESTION 1
When a control chart is used to monitor performance of a process, which of the following will be set by the project manager and the appropriate stakeholders to reflect the point(s) at which corrective action will be taken to prevent exceeding the specification limits?

  • A. Upper and lower control limits
  • B. Upper and lower specification limits
  • C. Process mean
  • D. Data points

Answer: A

NEW QUESTION 2
Which process determines the risks that might affect the project?

  • A. Perform Qualitative Risk Analysis
  • B. Identify Risks
  • C. Plan Risk Management
  • D. Perform Quantitative Risk Analysis

Answer: B

NEW QUESTION 3
Which characteristic is unique to project work and does not apply to operational work?

  • A. Performed by individuals
  • B. Limited by constraints
  • C. Temporary
  • D. Performed to achieve organizational objectives

Answer: C

NEW QUESTION 4
Which of the following tools or techniques is used for Estimate Activity Durations?

  • A. Critical path method
  • B. Rolling wave planning
  • C. Precedence diagramming method
  • D. Parametric estimating

Answer: D

NEW QUESTION 5
Within project integration management, the statement of work (SOW) references which aspects of the project?

  • A. Strategic plan, business need, and product scope description
  • B. Contract, enterprise environmental factors, and organizational process assets
  • C. Business plan, project management plan, and project schedule
  • D. Product lifecycle, business objective, and management strategy

Answer: A

NEW QUESTION 6
A project team attempts to produce a deliverable and finds that they have neither the expertise nor the time to complete the deliverable in a timely manner. This issue could have been avoided if they had created and followed a:

  • A. risk management plan
  • B. human resource management plan
  • C. scope management plan
  • D. procurement management plan

Answer: D

NEW QUESTION 7
Which piece of information is part of the WBS Dictionary?

  • A. Responsible organization
  • B. Change requests
  • C. Validated deliverables
  • D. Organizational process assets

Answer: A

NEW QUESTION 8
A project manager needs to deliver the project 2 weeks before the planned date without changing the scope. Which of the following techniques may be applied to reevaluate the schedule?

  • A. What-if scenario analysis
  • B. Critical chain method
  • C. Schedule crashing
  • D. Resource leveling

Answer: C

NEW QUESTION 9
The following is a network diagram for a project.
PMP dumps exhibit
What is the critical path for the project?

  • A. A-B-C-F-G-I
  • B. A-B-C-F-H-I
  • C. A-D-E-F-G-I
  • D. A-D-E-F-H-I

Answer: A

NEW QUESTION 10
Which of the following processes includes prioritizing risks for subsequent further analysis or action by assessing and combining their probability of occurrence and impact?

  • A. Qualitative risk analysis
  • B. Quantitative risk analysis
  • C. Risk management planning
  • D. Risk response planning

Answer: A

NEW QUESTION 11
Which of the following outputs from the Control Schedule process aids in the communication of schedule variance (SV), schedule performance index (SPI), or any performance status to stakeholders?

  • A. Performance organizations
  • B. Schedule baselines
  • C. Work performance measurements
  • D. Change requests

Answer: C

NEW QUESTION 12
Which of the following choices is a contract closure tool or technique?

  • A. Contract plan
  • B. Procurement plan
  • C. Closure process
  • D. Procurement audits

Answer: D

NEW QUESTION 13
Which characteristic do projects and operational work share in common?

  • A. Performed by systems
  • B. Constrained by limited resources
  • C. Repetitiveness
  • D. Uniqueness

Answer: B

NEW QUESTION 14
The progressive detailing of the project management plan is called:

  • A. expert judgment.
  • B. rolling wave planning.
  • C. work performance information.
  • D. specification.

Answer: B

NEW QUESTION 15
What is the definition of Direct and Manage Project Execution?

  • A. Integrating all planned activities
  • B. Performing the activities included in the plan
  • C. Developing and maintaining the plan
  • D. Execution of deliverables

Answer: B

NEW QUESTION 16
A contract management plan is a subsidiary of what other type of plan?

  • A. Resource plan
  • B. Project management plan
  • C. Cost control plan
  • D. Expected monetary value plan

Answer: B

NEW QUESTION 17
What quality control tool graphically represents how various elements of a system interrelate?

  • A. Control chart
  • B. Flowchart
  • C. Run chart
  • D. Pareto chart

Answer: B