It is more faster and easier to pass the Microsoft 70-348 exam by using Vivid Microsoft Managing Projects and Portfolios with Microsoft PPM (beta) questuins and answers. Immediate access to the Avant-garde 70-348 Exam and find the same core area 70-348 questions with professionally verified answers, then PASS your exam with a high score now.

NEW QUESTION 1
The SharePoint Farm administrator for a company installs Microsoft PPM and grants you administrative rights for PWA. The PWA instance is accessible at the URL: https://AppServer/Live.
You determine that the client needs to implement a Resource Breakdown Structure (RBS) to provide access to projects.
You need to ensure that the RBS is implemented. What should you do first?

  • A. Run the Set-SPProjectPermissionMode Windows PowerShell cmdlet.
  • B. Ask the SharePoint administrator to run the Set-SPProjectPermissionMode Windows PowerShell cmdlet.
  • C. From Settings, select Manage Groups.
  • D. From Site Settings, activate the Project Web App Connectivity feature.

Answer: B

NEW QUESTION 2
HOTSPOT
You are a project manager for an organization that uses visibility projects in Microsoft PPM. For each of the following statements, select Yes if the statement is true. Otherwise, select
No.
70-348 dumps exhibit

  • A. Mastered
  • B. Not Mastered

Answer: A

Explanation:
References:
https://support.office.com/en-gb/article/Publish-a-project-b4c7593d-0844-4d28-bf2c- 5ddff2498e33

NEW QUESTION 3
DRAG DROP
You are a project manager in an organization that is using Microsoft PPM. You are managing a 12-month project. Resources have been working on the project for six months.
You need to determine how the project is tracking against the initial goals in terms of duration, work and cost.
Which three actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area, and arrange them in the correct order.
70-348 dumps exhibit

  • A. Mastered
  • B. Not Mastered

Answer: A

Explanation:
References:
https://support.office.com/en-us/article/Create-or-update-a-baseline-or-an-interim-plan-7E775482-AC84-4F4A-BBD0-592F9AC91953

NEW QUESTION 4
HOTSPOT
You create a new project plan. You plan to take a snapshot of the project before and after the project start date.
For each of the following statements, select Yes if the statement is true. Otherwise, select
No.
70-348 dumps exhibit

  • A. Mastered
  • B. Not Mastered

Answer: A

Explanation:
The first baseline happens after the planning stage of the project. It is a snapshot of the planned timescales.
At the start of a project, when the manager has all the tasks in place, the people are assigned and the money is budgeted, he creates a baseline of data for his project so that he can measure its progress.
References:
https://support.office.com/en-us/article/Create-or-update-a-baseline-or-an-interim-plan-7E775482-AC84-4F4A-BBD0-592F9AC91953

NEW QUESTION 5
Your organization is in the process of implementing Microsoft PPM.
You need to configure Microsoft PPM to ensure that project managers can choose the
tracking method for each of their projects.
On the Task Settings and Display page, what should you do?

  • A. Set the tracking method to Free form.
  • B. Select the check box Force project managers to use the progress reporting method specified above for all projects.
  • C. Clear the check box Force project managers to use the progress reporting method specified above for all projects.
  • D. Set the tracking method to Percent of work complete.

Answer: A

NEW QUESTION 6
You are a project manager using Microsoft PPM.
You need to create a new project that uses one of your company’s templates.
What are two ways to achieve the goal? Each correct answer presents a complete solution.

  • A. From Microsoft Project, select Enterprise.
  • B. In Project Center, select New, and then select the desired enterprise project type.
  • C. In Resource Center, select New.
  • D. From Microsoft Project, select Featured.

Answer: AB

NEW QUESTION 7
HOTSPOT
You are a project manager in a large organization. During the project, some tasks have slipped, but the dependencies are still valid.
You are reviewing the project’s Gantt chart.
70-348 dumps exhibit
Use the drop-down menus to select the answer choice that answers each question.
70-348 dumps exhibit

  • A. Mastered
  • B. Not Mastered

Answer: A

Explanation:
70-348 dumps exhibit

NEW QUESTION 8
You are a project manager for an organization that uses Microsoft PPM.
One of the project members creates a risk. You need to link the risk to a task.
What should you do?

  • A. On the Risk list, edit the project member risk and insert the identifier for the task that you must relate.
  • B. On the Risk list, enter in the details of the project member risk.
  • C. On the Schedule page, select Link Tasks.
  • D. On the Schedule page, select Related Items.

Answer: D

Explanation:
References:
https://pwmather.wordpress.com/2013/04/24/projectserver-2013-linking-list-items-to-tasks-and-other-list-items-ps2013-sp2013/

NEW QUESTION 9
DRAG DROP
You are project manager in your company’s PMO. You have permission to manage the Enterprise Global view in Microsoft PPM. Your organization works with many large multiyear projects often managed by more than one project manager.
You need to provide an Enterprise Global view that displays the fields necessary for your colleagues to control whether a task is published, who will be responsible for sending the task updates for the task, and who is responsible for approving updates from resources.
Which five actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.
70-348 dumps exhibit

  • A. Mastered
  • B. Not Mastered

Answer: A

Explanation:
70-348 dumps exhibit

NEW QUESTION 10
DRAG DROP
You are the Microsoft PPM administrator for a large organization.
You need to ensure that line managers can delegate timesheet approvals to their team members.
Which three actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area, and arrange them in the correct order.
70-348 dumps exhibit

  • A. Mastered
  • B. Not Mastered

Answer: A

Explanation:
References:
https://technet.microsoft.com/en-us/library/cc197631.aspx

NEW QUESTION 11
HOTSPOT
Your organization uses Microsoft PPM and Power BI to manage projects. You create status reports for projects by using Microsoft Excel files and Power BI Desktop. You plan to combine several specific reports into a single Power BI dashboard.
For each of the following statements, select Yes if the statement is true. Otherwise, select No.
70-348 dumps exhibit

  • A. Mastered
  • B. Not Mastered

Answer: A

Explanation:
70-348 dumps exhibit

NEW QUESTION 12
You are a project manager for an organization that uses Microsoft PPM. You plan each project in phases.
Team members must only see the assignments from a selected phase. All reports and project schedule views must reflect the entire project schedule, so the entire project is visible to the management team.
You need to configure Microsoft PPM. What should you do?

  • A. Set the Publish field to No for all tasks that need the assignments to be hidden from the team members.
  • B. Delete the assignments that are not ready to be published to the team members.
  • C. Set up a new security category for the management team.
  • D. Set the booking type to Proposed for all tasks that need the assignments to be hidden from the team members.

Answer: D

NEW QUESTION 13
DRAG DROP
You are a project manager in an organization that is using Microsoft PPM for work management.
You have already accepted all status updates in the Approval Center, but you are still unable to see the updates in your project schedule.
You need to ensure that status updates are reflected in your project schedule.
Which four actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.
70-348 dumps exhibit

  • A. Mastered
  • B. Not Mastered

Answer: A

Explanation:
70-348 dumps exhibit

NEW QUESTION 14
Your company has had several large projects fail due to cost overruns and the lack of available resources. These projects use an enterprise project type named Large IT Project and use a workflow to govern the approval of the projects. The workflow consists of four phases: Initiate, Plan, Execute, and Close.
You need to use Microsoft PPM to compare the value that a new project provides with the cost of implementing the project.
Which three configuration changes should you make? Each correct answer presents part of the solution.

  • A. Navigate to PWA Setting
  • B. Edit the Large IT Project project type, and in the Available Project Detail Page section, add the Strategic Impact form.
  • C. Create a project-level custom field that will be used to enter the total cost of a project.
  • D. Define your company’s strategic drivers, and enter them into the Strategic Impact form.
  • E. Create a project-level custom field that will be used to enter the value statements of why this project should be undertaken.
  • F. Define your company’s strategic drivers and enter them into the driver library.
  • G. In PWA Settings, edit and then save the stage informatio
  • H. In the Available Project Detail Page section, add the Strategic Impact form.

Answer: ABE

NEW QUESTION 15
HOTSPOT
You are the project manager for a real estate management company. You are using Microsoft Project to manage the development of a new restaurant. The schedule includes a task named Equipment delivery.
Your supplier states that they will start delivering stoves, refrigerators, and other equipment on June 9, 2021.
You need to modify the Equipment delivery task.
How should you configure the constraint for the task? To answer, select the appropriate option from each list in the answer area.
70-348 dumps exhibit

  • A. Mastered
  • B. Not Mastered

Answer: A

Explanation:
70-348 dumps exhibit

NEW QUESTION 16
......