Q1. - (Topic 1) 

Your organization uses a Microsoft Visual Studio Team Foundation Server (TFS) 2010 environment on a Windows Server 2008 R2 SP1 server. 

The Windows Server 2008 R2 SP1 server has a SQL Server 2008 R2 environment, as well as a Microsoft Office SharePoint Foundation 2010 environment. Your organization wants to perform an in-place upgrade to the 2013 version of TFS. 

You need to prepare the environment to meet the minimum requirements for the upgrade. 

What should you do? 

A. Upgrade SQL Server to SQL Server 2012 SP1. 

B. Add a test lab server. 

C. Upgrade the SharePoint Server to Microsoft Office SharePoint Server 2013, Enterprise edition. 

D. Upgrade all tiers to Windows Server 2012. 

Answer:

Explanation: http://msdn.microsoft.com/en-us/library/ff803410(v=vs.100).aspx 

Q2. - (Topic 2) 

You run a manual test on an application by using Microsoft Test Manager (MTM). You have the following testing requirements: 

. Collect the diagnostic data from the local machine, and 

. Collect the diagnostic data from a remote SQL Server. 

You need to identify the components required to configure the test environment to comply with these requirements. 

Which two components should you choose? (Each correct answer presents part of the solution. Choose two.) 

A. Configuration variables 

B. Data collectors 

C. Local and remote roles 

D. Build controller 

Answer: B,C 

Q3. - (Topic 1) 

You are preparing your network environment for a Microsoft Visual Studio Team Foundation Server 2012 (TFS) server. 

You want to install a new Microsoft SQL Server 2012 server to use as a data-tier server. 

You need to install the minimum SQL options that will support only the Microsoft Visual Studio TFS 2012 databases. 

Which three SQL options should you select? (Each correct answer presents part of the solution. Choose three.) 

A. Windows Authentication selected as the authentication mode 

B. Database Engine Services 

C. Analysis Services 

D. Full-Text Search (Full-Text and Semantic Extractions for Search in SQL 2012) 

E. Reporting Services 

Answer: A,D,E 

Q4. - (Topic 3) 

You are an automation engineer for your company. Your Scrum team is defining processes 

for how your team should deliver products for product owner approval. 

Your development team is deciding what the definition of done should be. 

You need to contribute a test suite that will confirm each user story's level of done. 

Which test should you perform? 

A. Integration 

B. Security 

C. Performance 

D. System 

Answer:

Q5. - (Topic 1) 

Your network environment includes a Microsoft Visual Studio Team Foundation Server (TFS) 2012 server. 

You need to rebuild both the Team Foundation Data Warehouse and the SQL Server Analysis Services Cube from scratch. 

What are two possible ways to achieve this goal? (Each correct answer presents a complete solution. Choose two.) 

A. Use Microsoft SQL Server Management Studio. 

B. Use SQL Server Business Intelligence Development Studio. 

C. Use Warehouse Control Web Service. 

D. Use the Reporting section in Team Foundation Administration Console. 

E. Restart SQL Server Analysis Services service, SQL Server service, and SQL Server Agent service by navigating to the Services option under Administrative Tools. 

Answer: C,D 

Q6. - (Topic 3) 

Your development team uses the Microsoft Visual Studio Scrum 2.0 process template. You are the scrum master. 

The product owner has created product backlog items and assigned them to a release. 

You need to work with the development team to estimate when the release will be completed. 

Which three actions should you perform? (Each correct answer presents part of the solution. Choose three.) 

A. Review the sprint backlog. 

B. Review the product backlog with the Forecast option set to on to determine if the release can be completed based on the team’s velocity. 

C. Have the team create tasks for each item in the product backlog and assign hour estimates to the task. 

D. Review the sprint burndown chart. 

E. Set each team member’s per day capacity. 

F. Establish a sprint duration and a sprint velocity. Create enough sprints to complete the release. 

G. Estimate effort for each item in the product backlog. 

Answer: B,F,G 

Explanation: By using the forecasting tool in Web Access, you can plan the number of Sprints it will take to complete a set of work. The forecasting tool is available only in the Product Backlog, not any of the Sprint Backlogs. Prior to being able to use the forecasting tool, your Product Backlog must have PBI and Bug work items already created with the effort specified. 

You can turn on forecasting by clicking the Off hyperlink next to Forecast on the right side of the backlog page. The first time you do this, Web Access prompts you for the Velocity. Using your Development Team’s Velocity, Web Access will add a Forecast column and horizontal lines to the Product Backlog. In the Forecast column, it will display the Sprint that it predicts the PBI or Bug work item will be developed in. 

Professional Scrum Development with Microsoft Visual Studio 2012 p.165 

Q7. - (Topic 3) 

You are developing an application that has several automated builds that build, perform code analysis, and unit test portions of your code. Your team also performs peer review for code changes in an informal manner. 

You need to meet the following requirements: 

. Provide documentation on quality checks and reviews for any changes to the code 

base. 

. Ensure code quality. 

. Maintain your team’s efficiency. 

What should you do? 

A. Institute gated check-ins to the build process. 

B. Deny developers check-in permissions. Allow them to shelve changes and have a senior team member check in the shelve-set after review. 

C. Utilize the Code Review work items and workflow before check-ins. 

D. Perform a weekly code review on subset of recent check-ins. 

Answer:

Q8. DRAG DROP - (Topic 2) 

You are using Microsoft Test Manager (MTM) to manage your testing efforts. 

You plan to identify which tests are impacted by changes to the code. 

You need to view a list of recommended tests from the Recommended tests view. 

What should you do? (To answer, move the three appropriate actions from the list of 

actions to the answer area and arrange them in the correct order.) 

Answer:  

Q9. DRAG DROP - (Topic 2) 

You are a test developer using Microsoft Test Manager (MTM). 

You are editing a test plan for a product. 

You need to supply a new custom configuration variable in the configuration setting for one 

of the test cases. 

In which order should you perform the actions in MTM? To answer, move all actions from 

the list of actions to the answer area and arrange them in the correct order. 

Answer:  

Q10. - (Topic 1) 

Your software development team works within a single team project in a team project collection. You have one build controller and one build agent associated to your team project collection. 

Multiple build definitions are configured. You notice that builds occasionally wait in the queue for a long time before the build starts. 

You need to reduce the amount of time that your builds wait in the queue. 

What should you do? 

A. Change the Name filter argument on your build definition so that the build agent is found more quickly. 

B. Configure your build agent to run multiple builds at the same time. 

C. Configure additional build controllers, and associate them to the build agent already in use. 

D. Configure additional build agents, and associate them to the build controller already in use. 

Answer:

Explanation: http://social.msdn.microsoft.com/Forums/vstudio/en-US/b6d12dfa-5481-41d5-8012-1f19277b358c/tfs-2012-build-taking-a-lot-of-time?forum=tfsbuild