We provide real CAPM exam questions and answers braindumps in two formats. Download PDF & Practice Tests. Pass PMI CAPM Exam quickly & easily. The CAPM PDF type is available for reading and printing. You can print more and practice many times. With the help of our PMI CAPM dumps pdf and vce product and material, you can easily pass the CAPM exam.

Also have CAPM free dumps questions for you:

NEW QUESTION 1

Which of the following are three inputs to the risk register?

  • A. Risk register updates, stakeholder register, and quality management plan
  • B. Communication management plan, enterprise environmental factors, and activity duration estimates
  • C. Risk management plan, activity cost estimates, and project documents
  • D. Project scope statement, organizational process assets, and scope baseline

Answer: C

NEW QUESTION 2

Stakeholder communication requirements should be included as a component of:

  • A. enterprise environmental factors
  • B. organizational process assets
  • C. the project management plan
  • D. the stakeholder register

Answer: C

NEW QUESTION 3

A project manager seeking insight on previous stakeholder management plans and their effectiveness should evaluate:

  • A. Historical information and the lessons-learned database.
  • B. Historical information and the stakeholder register.
  • C. Organizational process assets and the lessons-learned database.
  • D. Project documents and historical informatio

Answer: A

NEW QUESTION 4

Which enterprise environmental factors may influence Plan Schedule Management?

  • A. Cultural views regarding time schedules and professional and ethical behaviors
  • B. Historical information and change control procedures
  • C. Risk control procedures and the probability and impact matrix
  • D. Resource availability and organizational culture and structure

Answer: D

NEW QUESTION 5

An input of the Create WBS process is:

  • A. requirements documentation.
  • B. scope baseline.
  • C. project charter.
  • D. validated deliverable

Answer: A

NEW QUESTION 6

Another name for an Ishikawa diagram is:

  • A. cause and effect diagram.
  • B. control chart.
  • C. flowchart.
  • D. histogra

Answer: A

NEW QUESTION 7

A project manager who communicates to the project team though email is using which type of communication?

  • A. Formal
  • B. Informal r
  • C. Horizontal
  • D. Unofficial

Answer: B

NEW QUESTION 8

Which of the following is an estimating technique that uses the values of parameters from previous similar projects for estimating the same parameter or measure for a current project?

  • A. Reserve analysis
  • B. Three-point estimating
  • C. Parametric estimating
  • D. Analogous estimating

Answer: D

NEW QUESTION 9

Which of the following correctly explains the term "progressive elaboration'?

  • A. Changing project specifications continuously
  • B. Elaborate tracking of the project progress
  • C. Elaborate tracking of the project specifications with a change control system
  • D. Project specifications becoming more explicit and detailed as the project progresses

Answer: D

NEW QUESTION 10

Which type of analysis is used to examine project results through time to determine if performance is improving or deteriorating?

  • A. Control chart
  • B. Earned value
  • C. Variance
  • D. Trend

Answer: D

NEW QUESTION 11

Which input will be used when tasked with developing the human resource plan?

  • A. Project management plan
  • B. Activity resource requirements
  • C. Resource calendar
  • D. Project staff assignments

Answer: B

NEW QUESTION 12

A reward can only be effective if it is:

  • A. Given immediately after the project is completed.
  • B. Something that is tangible.
  • C. Formally given during project performance appraisals.
  • D. Satisfying a need valued by the individua

Answer: D

NEW QUESTION 13

In which phase of team building activities do team members begin to work together and adjust their work habits and behavior to support the team?

  • A. Performing
  • B. Storming
  • C. Norming
  • D. Forming

Answer: C

NEW QUESTION 14

When painting a bedroom, preparing the walls can be done while the paint is being chosen. This is an example of a:

  • A. lead
  • B. lag
  • C. mandatory dependency
  • D. internal dependency

Answer: A

NEW QUESTION 15

Which Collect Requirements output links the product requirements to the deliverables that satisfy them?

  • A. Requirements documentation
  • B. Requirements traceability matrix
  • C. Project management plan updates
  • D. Project documents updates

Answer: B

NEW QUESTION 16

In which Project Management Process Group is the project charter developed?

  • A. Monitoring and Controlling
  • B. Executing
  • C. Initiating
  • D. Planning

Answer: C

NEW QUESTION 17

A large portion of a projects budget is typically expended on the processes in which Process Group?

  • A. Executing
  • B. Planning
  • C. Monitoring and Controlling
  • D. Closing

Answer: B

NEW QUESTION 18

Which of the following is an input to Develop Human Resource Plan?

  • A. Team performance assessment
  • B. Roles and responsibilities
  • C. Staffing management plan
  • D. Enterprise environmental factors

Answer: D

NEW QUESTION 19

In which Process Group are lessons learned documented?

  • A. Planning
  • B. Closing
  • C. Executing
  • D. Initiating

Answer: B

NEW QUESTION 20

The Perform Integrated Change Control process occurs in which Process Group?

  • A. Initiating
  • B. Executing
  • C. Monitoring and Controlling
  • D. Planning

Answer: C

NEW QUESTION 21

When can pre-assignment of project team members occur?

  • A. When the project uses capital expenditures
  • B. When the required staff can be acquired from outside sources
  • C. When the project would be ignored due to travel expenses
  • D. When the project is the result of specific people being promised as part of a competitive proposal

Answer: D

NEW QUESTION 22

Which process is usually a rapid and cost-effective means of establishing priorities for Plan Risk Responses?

  • A. Identify Risks
  • B. Plan Risk Management
  • C. Perform Qualitative Risk Analysis
  • D. Perform Quantitative Risk Analysis

Answer: C

NEW QUESTION 23

What provides information regarding the ways people, teams, and organizational units behave?

  • A. Organizational chart
  • B. Organizational theory
  • C. Organizational structure
  • D. Organizational behavior

Answer: B

NEW QUESTION 24

Which of the following is an input to the Perform Qualitative Risk Analysis process?

  • A. Risk register
  • B. Risk data quality assessment
  • C. Risk categorization
  • D. Risk urgency

Answer: A

NEW QUESTION 25

During which process would stakeholders provide formal acceptance of the completed project scope?

  • A. Perform Quality Control
  • B. Verify Scope
  • C. Control Scope
  • D. Develop Schedule

Answer: B

NEW QUESTION 26
......