We provide real CAPM exam questions and answers braindumps in two formats. Download PDF & Practice Tests. Pass PMI CAPM Exam quickly & easily. The CAPM PDF type is available for reading and printing. You can print more and practice many times. With the help of our PMI CAPM dumps pdf and vce product and material, you can easily pass the CAPM exam.
Also have CAPM free dumps questions for you:
NEW QUESTION 1
Which of the following are three inputs to the risk register?
Answer: C
NEW QUESTION 2
Stakeholder communication requirements should be included as a component of:
Answer: C
NEW QUESTION 3
A project manager seeking insight on previous stakeholder management plans and their effectiveness should evaluate:
Answer: A
NEW QUESTION 4
Which enterprise environmental factors may influence Plan Schedule Management?
Answer: D
NEW QUESTION 5
An input of the Create WBS process is:
Answer: A
NEW QUESTION 6
Another name for an Ishikawa diagram is:
Answer: A
NEW QUESTION 7
A project manager who communicates to the project team though email is using which type of communication?
Answer: B
NEW QUESTION 8
Which of the following is an estimating technique that uses the values of parameters from previous similar projects for estimating the same parameter or measure for a current project?
Answer: D
NEW QUESTION 9
Which of the following correctly explains the term "progressive elaboration'?
Answer: D
NEW QUESTION 10
Which type of analysis is used to examine project results through time to determine if performance is improving or deteriorating?
Answer: D
NEW QUESTION 11
Which input will be used when tasked with developing the human resource plan?
Answer: B
NEW QUESTION 12
A reward can only be effective if it is:
Answer: D
NEW QUESTION 13
In which phase of team building activities do team members begin to work together and adjust their work habits and behavior to support the team?
Answer: C
NEW QUESTION 14
When painting a bedroom, preparing the walls can be done while the paint is being chosen. This is an example of a:
Answer: A
NEW QUESTION 15
Which Collect Requirements output links the product requirements to the deliverables that satisfy them?
Answer: B
NEW QUESTION 16
In which Project Management Process Group is the project charter developed?
Answer: C
NEW QUESTION 17
A large portion of a projects budget is typically expended on the processes in which Process Group?
Answer: B
NEW QUESTION 18
Which of the following is an input to Develop Human Resource Plan?
Answer: D
NEW QUESTION 19
In which Process Group are lessons learned documented?
Answer: B
NEW QUESTION 20
The Perform Integrated Change Control process occurs in which Process Group?
Answer: C
NEW QUESTION 21
When can pre-assignment of project team members occur?
Answer: D
NEW QUESTION 22
Which process is usually a rapid and cost-effective means of establishing priorities for Plan Risk Responses?
Answer: C
NEW QUESTION 23
What provides information regarding the ways people, teams, and organizational units behave?
Answer: B
NEW QUESTION 24
Which of the following is an input to the Perform Qualitative Risk Analysis process?
Answer: A
NEW QUESTION 25
During which process would stakeholders provide formal acceptance of the completed project scope?