NEW QUESTION 1

The process of confirming human resource availability and obtaining the team necessary to complete project activities is known as:

  • A. Plan Human Resource Management.
  • B. Acquire Project Team.
  • C. Manage Project Team.
  • D. Develop Project Tea

Answer: B

NEW QUESTION 2

Which action should a project manager take to ensure that the project management plan is effective and current?

  • A. Conduct periodic project performance reviews.
  • B. Identify quality project standards.
  • C. Follow ISO 9000 quality standards.
  • D. Complete the quality control checklis

Answer: A

NEW QUESTION 3

The iterative and interactive nature of the Process Groups creates the need for the processes in which Knowledge Area?

  • A. Project Communications Management
  • B. Project Integration Management
  • C. Project Risk Management
  • D. Project Scope Management

Answer: B

NEW QUESTION 4

A full-time project manager with low to moderate authority and part-time administrative staff is working in an organizational structure with which type of matrix?

  • A. Strong
  • B. Weak
  • C. Managed
  • D. Balanced

Answer: D

NEW QUESTION 5

The organization's perceived balance between risk taking and risk avoidance is reflected in the risk:

  • A. Responses
  • B. Appetite
  • C. Tolerance
  • D. Attitude

Answer: A

NEW QUESTION 6

An output of the Validate Scope process is:

  • A. A requirements traceability matrix.
  • B. The scope management plan.
  • C. Work performance reports.
  • D. Change request

Answer: D

NEW QUESTION 7

Which cost estimate technique includes contingencies to account for cost uncertainty?

  • A. Vendor bid analysis
  • B. Three-point estimates
  • C. Parametric estimating
  • D. Reserve analysis

Answer: D

NEW QUESTION 8

A tool and technique used during the Perform Qualitative Risk Analysis process is:

  • A. risk data quality assessment.
  • B. variance and trend analysis.
  • C. data gathering and representation techniques.
  • D. risk audit

Answer: A

NEW QUESTION 9

The degree, amount, or volume of risk that an organization or individual will withstand is known as its risk:

  • A. Analysis
  • B. Appetite
  • C. Tolerance
  • D. Response

Answer: C

NEW QUESTION 10

While processes in the Planning Process Group seek to collect feedback and define project documents to guide project work, organizational procedures dictate when the project planning:

  • A. ends.
  • B. begins.
  • C. delays.
  • D. deviate

Answer: A

NEW QUESTION 11

What is the probability of occurrence if the risk rating is 0.56 and the impact if the risk does occur is very high (0.80)?

  • A. 0.45
  • B. 0.56
  • C. 0.70
  • D. 1.36

Answer: C

NEW QUESTION 12

Status of deliverables, implementation status for change requests, and forecasted estimates to complete are examples of:

  • A. Earned value management.
  • B. Enterprise environmental factors.
  • C. Organizational process assets.
  • D. Work performance informatio

Answer: D

NEW QUESTION 13

What name(s) is (are) associated with the Plan-Do-Check-Act cycle?

  • A. Pareto
  • B. Ishikawa
  • C. Shewhart-Deming
  • D. Delphi

Answer: C

NEW QUESTION 14

How many Project Management Process Groups are there?

  • A. 3
  • B. 4
  • C. 5
  • D. 6

Answer: C

NEW QUESTION 15

The progressive detailing of the project management plan is called:

  • A. expert judgment.
  • B. rolling wave planning.
  • C. work performance information.
  • D. specificatio

Answer: B

NEW QUESTION 16

Which of the following is a project constraint?

  • A. Twenty-five percent staff turnover is expected.
  • B. The technology to be used is cutting-edge.
  • C. Project leadership may change due to volatile political environment.
  • D. The product is needed in 250 day

Answer: D

NEW QUESTION 17

What is a deliverable-oriented, hierarchical decomposition of the work to be executed to accomplish the project objectives and create the required deliverables?

  • A. Organizational breakdown structure (OBS)
  • B. Work performance information
  • C. Work package
  • D. Work breakdown structure (WBS)

Answer: D

NEW QUESTION 18

The most appropriate project life cycle model for an environment with a high level of change and extensive stakeholder involvement in projects is:

  • A. adaptive
  • B. reflexive
  • C. predictive
  • D. iterative

Answer: A

NEW QUESTION 19

In a construction project schedule, what is the logical relationship between the delivery of the concrete materials and the pouring of concrete?

  • A. Start-to-start (SS)
  • B. Start-to-finish (SF)
  • C. Rnish-to-finish (FF)
  • D. Finish-to-start (FS)

Answer: D

NEW QUESTION 20

Perform Quality Control is accomplished by:

  • A. Identifying quality standards that are relevant to the project and determining how to satisfy them.
  • B. Monitoring and recording the results of executing the quality activities to assess performance and recommend necessary changes.
  • C. Ensuring that the entire project team has been adequately trained in quality assurance processes.
  • D. Applying Monte Carlo, sampling, Pareto analysis, and benchmarking techniques to ensure conformance to quality standards.

Answer: B

NEW QUESTION 21

Which item is a formal proposal to modify any document, deliverable, or baseline?

  • A. Change request
  • B. Requirements documentation
  • C. Scope baseline
  • D. Risk urgency assessment

Answer: A

NEW QUESTION 22

In Plan Risk Management, which of the management plans determines who will be available to share information on various risks and responses at different times and locations?

  • A. Schedule
  • B. Quality
  • C. Communications
  • D. Cost

Answer: C

NEW QUESTION 23

Which action is included in the Control Costs process?

  • A. Identify how the project costs will be planned, structured, and controlled
  • B. Determine policies, objectives, and responsibilities to satisfy stakeholder needs
  • C. Develop an approximation of the monetary resources needed to complete project activities
  • D. Monitor cost performance to isolate and understand variances from the approved cost baseline

Answer: D

NEW QUESTION 24

Which of the following is an output of Close Procurements?

  • A. Accepted deliverables
  • B. Organizational process assets updates
  • C. Managing stakeholder expectations
  • D. Performance reports

Answer: B

NEW QUESTION 25

When does the project team determine which dependencies are discretionary?

  • A. Before the Define Activities process
  • B. During the Define Activities process
  • C. Before the Sequence Activities process
  • D. During the Sequence Activities process

Answer: D

NEW QUESTION 26
......