Q1. A technician is installing a rack mounted server into a rack in a datacenter with CRAC units and blanking panels. Blanking panels are used to:

A. lower the UPS power requirements.

B. limit airflow leakage in the rack.

C. limit the amount of servers that will fit into the rack.

D. color match the server color.

Answer: B

Q2. Two new applications have been added to a working server. The server response is now very slow. An appropriate plan of action is to:

A. uninstall each server application and reinstall the two new applications.

B. install another application to see if this improves the server response time.

C. install antivirus and malware software.

D. uninstall the newly installed applications one at a time.

Answer: D

Q3. A host server in a small business environment does not have virtual switching configured. The NIC on aguestis configured with an IP address that is on a different subnet from thehost server. Which of the followingwouldMOSTlikely happen in this case?

A. The guest will not have network access to the host or network resources.

B. The guest would have access to all network resources.

C. The guest would have network access to everything but the host.

D. The guest will have network access to the host server.

Answer: A

Q4. A company is being audited by its operating system vendor. The company needs to report the number of operating systems in use, the versions of the operating systems, and the product keys. Which of the following will be MOST helpful in passing the audit?

A. Asset management documentation

B. Change management logs

C. Service manuals

D. Server baselines

Answer: A

Q5. Several of the finance department computers are experiencing timeouts while in their financial program. The program will not open or close; however, the previous day the program was running without issues. Which of the following is MOST likely the cause of this problem?

A. Service priority

B. Rogue processes

C. Firewall problem

D. Processor affinity

Answer: B

Q6. A server has recently been configured as a network firewall. After the firewall was configured, users could no longer access a remote server. Which of the following, if properly configured on the firewall, will allow users to have secure access to the remote server?(Select TWO).

A. Allow TCP port 21

B. Allow TCP port 22

C. Allow TCP port 23

D. Allow TCP port 25

E. Allow TCP port 161

F. Allow TCP port 3389

Answer: B,F

Q7. Anadministrator isbuilding a web server to host an online banking application. Theserver should not have access to the internal network, andonly ports that are used by theapplication should be opened. Whichof the following MUSTbe implemented to meet the business requirements?

A. Add the server to the internal network and use IPSec to encrypt communication between the web server and other devices.

B. Use an ISA server to block access to the internal network.

C. Use VPN to block all ports that are not used by the application.

D. Use the company firewall to block all ports that are not used by the application.

Answer: D

Q8. A datacenter is in a geologically active area and has no earthquake abatement installed.Which of thefollowingdrive typesisBEST for general server use?

A. Solid state drives

B. High RPM drives

C. Low RPM drives

D. USB drives

Answer: A

Q9. A server has a faulty hard drive, and the administrator needs to replace the hard drive while it is running. The server needs to support which of the following drives?

A. Hot swappable

B. Hot spare

C. SAS

D. USB

E. Firewire

Answer: A

Q10. A line-of-business software patch notification is received. The notification indicates that version 5.0 of the software has new features that the accounting department has been expecting.The update requires a new version of the OS and new version of SQL on the server. Which of the following should the administrator performFIRST?

A. Schedule downtime to update the OS and SQL on the server.

B. Download and test the new version.

C. Develop a plan to build a test server.

D. Request feedback from the accounting department.

Answer: C